Important Thumb Rules for Estimation in Civil Engineering
We can’t calculate each and everything in the field.
Sometimes we have to act quickly to move on. Every professional have maintained their own set of thumb rules.
What is Thumb Rule?
At first, we have to understand the meaning of thumb rule before jumping into the discussion.
- Thumb rules are “ Approximate Value”.
- Thumb Rules has no unit systems
We use the thumb rules for almost in every calculation like concrete calculation, manpower estimation, the material requirement for plastering, wastage’s calculation, brickwork calculation, etc.,
For example,
What is the requirement of bricks for 1 Cum? As per the calculation 625 nos.
But we Say Approx 600 nos. It is called as a thumb rule. Because we can not estimate every time according to the individual requirement.
Thumb rule for Manpower Productivity Estimation
Manpower productivity thumb rules will be useful to calculate the total manpower required for your next schedule.
SI | MANPOWER | ACTIVITY | OUTPUT - 8 HOURS |
---|---|---|---|
1 | Mason - 1 Male mazdoor - 0.75 Female Mazdoor - 0.5 | Brick Work | 45 Cft |
2 | Mason - 1 Male mazdoor - 1 Female Mazdoor - 0.5 | Wall plastering | 120 Sft |
3 | Mason - 1 Male mazdoor - 0.75 Female Mazdoor - 0.5 | Ceiling Plastering | 90 Soft |
4 | Carpenter-2.25 Foreman- 0.2 Helper- 2.25 | Shuttering Work | 11 Sqm |
5 | Bar Bender - 1 Nos Helper - 1 Nos | Steel Work | 100 Kg |
6 | Tile Mason - 1 Nos Helper - 1 Nos | Tile Work | 10 Sqm |
7 | Mason - 2 Male mazdoor - 1.75 Female Mazdoor - 1.75 | Block Work | 2 Cum |
8 | Male Coolie - 5 Nos Female Coolie - 4 Nos | Earth Digging | 1000 Cft |
Thumb rule for concrete work
The concrete ingredients will be vary based on the mix ratio.
For Example,
If the Plinth area is 100 Sq.ft (10 x 10) and the required concrete volume is 100 x 0.04 = 4 Cum with M5 mix ratio means
Now from the below table which is for 1 m3
Required Concrete ingredients for 4 m3 of M5 is
Cement – 2.77 x 4 = 11.08 bags
Sand – 0.48 x 4 = 1.92 cum
Coarse aggregate = 0.96 x 4 = 3.84 cum
Thumb Rule of Concrete material requirement
GRADE | RATIO | CEMENT IN BAGS | SAND IN CUM | COARSE AGGREGATES IN CUM |
---|---|---|---|---|
M5 | 1:5:10 | 2.77 | 0.48 | 0.96 |
M7.5 | 1:4:8 | 3.41 | .047 | 0.95 |
M10 | 1:3:6 | 4.44 | 0.46 | 0.92 |
M15 | 1:2:4 | 6.34 | 0.44 | 0.88 |
M20 | 1:1.5:3 | 8.06 | 0.42 | 0.84 |
M25 | 1:1:2 | 11.09 | 0.39 | 0.77 |
Must Read:- What is water cement Ratio
Thumb rule for Plastering Work
For plastering, the material quantity will vary based on the different mix ratios like concrete and the thumb rule for plastering work has listed below.
TYPE OF PLASTERING | MIX RATIO | THICKNESS IN MM | CEMENT BAGS/SQM | SAND CUM/SQM |
---|---|---|---|---|
Inner Plastering | 1:3 | 15 | 0.16 | 0.017 |
External Plastering | 1:4 | 20 | 0.17 | 0.024 |
Rough Plastering | 1:5 | 16 | 0.11 | 0.020 |
Ceiling Plastering | 1:2 | 12 | 0.17 | 0.012 |
To know more How to calculate material for Plastering work
Thumb rule for Brick Work
The size of brick 190mm x 90mm x 90mm
Number of bricks per cum = 500 Nos
Must read: How to calculate the number of bricks
MIX RATIO AND BRICKWORK THICKNESS | MORTAR THICKNESS IN MM | CEMENT IN BAGS | SAND IN CUM |
---|---|---|---|
1:6 200mm Thk | 10 | 1.4 / Cum | 0.30 |
1:5 200mm Thk | 10 | 1.7 / Cum | 0.25 |
1:4 100mm Thk | 10 | 0.15 / Sqm | 0.035 |
1:5 200mm Thk Block | 10 | 0.15 / Cum | 0.020 |
Thumb rule for Steel in RCC
The steel cost very expensive compared to other construction material and the excess purchase of steel requirement impact the project budget. A good designer restrains steel utilization.
TYPE OF STRUCTURE | STEEL KG/SFT |
---|---|
Residential Building | 2.5 to 4.5 |
Commercial Building | 4.5 to 5.5 |
Mass Project Tall or heavy Structure | 6 to 8 |
The steel percentage against concrete volume will vary based on the structural element and the minimum and maximum percentage of steel utilization have listed below as per IS standard.
The Thumb rule for steel in RCC has listed below.
STRUCTURAL ELEMENT | PERCENTAGE OF STEEL IN CONCRETE |
---|---|
Slab | 1% |
Beam | 1% to 2% |
Column | 2.5% |
Must Read: How to calculate steel weight for Reinforcement
Example calculation:
Steel quantity = Volume of Concrete x Density of Steel x % of Steel.
For example, if a volume of concrete 1 cum for a slab.
Approx Steel requirement = 1 x 7850 x 1% = 78.5 Kg/Cum.
Read: Bar bending Shape codes
Thumb rule for shuttering work
The shuttering work is called by another name “Form Work” because it gives a uniform shape and smoothness for the concrete. Generally, it takes 10% to 15% of the cost of the total budget.
The Thumb rule for shuttering work is listed below.
TYPE OF CONCRETE ELEMENT | NO OF TIMES SQM PER CUM |
---|---|
Foundation | 2 to 3 times of concrete volume |
Column | 11 to 13 times of concrete volume |
Beam | 11 to 12 times of concrete volume |
Slab | 6 to 8 times of concrete volume |
For example, if the slab concrete volume 1 cum then the approx shuttering requirement is 1 x 6 = 6 Sqm.
If we have missed anything please do let us know to update!
Do you have any kind of thumb rules for yourself? If so share it with us in the comment section we would like to also learn something from you.
thanks to
CIVIL PLANETS
Er.SP.ASWINPALANIAPPAN., M.E.,(Strut/.,)
Structural Engineer
Madras Terrace Architectural Works
We can provide what you want with your customization, and we will assure you to deliver the same.
ReplyDeleteExpert Tips on Staying Safe During Prefab Steel Construction
This post is extremely radiant. I extremely like this post. It is outstanding amongst other posts that I’ve read in quite a while. Much obliged for this better than average post. I truly value it! vastu consultant india
ReplyDelete