Thursday, 10 August 2017

Bar Bending Schedule (BBS)

What is meant by Bar Bending Schedule (BBS)

Bar Bending Schedule, commonly referred to as “BBS” is a comprehensive list that describes the location, mark, type, size, length and number, and bending details of each bar or fabric in a Reinforcement Drawing of a Structure.
This process of listing the location, type and size, number of and all other details is called “Scheduling”. In context of Reinforcement bars, it is called bar scheduling. In short, Bar Bending Schedule is a way of organizing rebars for each structural unit, giving detailed reinforcement requirements.
REINFORCEMENT (R/f)
  • Introduction
Reinforced concrete is the most commonly used structural material in engineering construction. Although concrete is strong in resisting compressive stress, it is weak intention. Hence to withstand tensional stresses, steel is need in concrete. The reinforcement in concrete may be simple bars or rods bend and tied to a given schedule with stirrups. The nominal diameters of bars used at site were Y10, Y12, Y16, Y20, Y25 and R6.
Steel is supplied in two basic types.
1. Mild steel (250 N/mm2)
2. Tor steel (460 N/mm2)
  • Bar code            
Indication of Reinforcement in Drawings
Engineering drawings is a language to communicate with details. Therefore there is a standard to indicate reinforcement in drawing such as,
5Y10- 001- 150:-Which means 5 Number of Tor steel, 10mm Diameter, Bar mark 001, At 150mm CRS. At                                                      bottom face.
Bar location can be vary as follows:
Notation for Slab-
T1 -Top outer layer, T2 -Top second layer
B1 -Bottom outer layer, B2 -Bottom second layer
  • Cutting and Bending of Bars
      There is a steel yard in the site for storing, cutting and bending of bars. Reinforcement bars are cut into required lengths and bent into required shapes shown on the bar schedule either manually or by means of machinery.
       In manual operations, laborers used the bar bending bench on which strong nails are fixed and GI pipes with suitable lengths to bend the bars. That is used for smaller diameter bars. For bending of larger diameter bars, bar bending machine is used. After bending all reinforcement bars were bundled and clearly numbered according to the bar mark so that steel fixers will not face any difficulty when fixing them.
Picture1
Fig.1 :- Bar bending work
  • Prepare bar schedule (important considerations)
 Reinforcement Bar Schedule
      Reinforcement Bar Schedule is prepared in a standard manner. The bar bending schedule should be prepared and it should be submitted to the steel bar steel yard to cut and to bend the bars for purposes, because bar bending schedule is the simplest of details what is in the drawings which can easy to under stand for bar benders. It contains all the details needed for fabrication of steel.Those details are bar mark, bar type and size, number of units, length of a bar, shape code, distance between stirrups (column, plinth, beam) etc.
Advantages of the Bar Schedule:
  • By preparing a bar schedule, and arranging them according to the lengths, it will lead to an economical bar cutting, reduce the bar cutting wastages.
  • It is easy to manage the reinforcement stock required for identified time duration.
  • It will help to fabrication of R/F with structure.
Calculating weight of the steel
 While prepared the bar schedule, we used the unit weight of reinforcement bar.
Nominal Diameter of the bar (mm)Unit weight (kg/m)
R60.222
R100.610
T100.617
T120.888
T161.580
T202.469
T253.858
T326.313
Table- Unit weight of the bar
It is necessary to be careful about length when preparing bar schedules. In case of bending, bar length will increased at the bending positions.
  • Minimization of bar cutting wastage
 In the site several steps were adopted for that purpose. Those are, Use of 12m long r/f bars rather than using shorter bars. For example 6m bars off cuts of 12m bars were used to prepare stools, separators etc.
  • Off cuts of larger diameter (25mm) bars-for spacer bars
  • Off cuts of smaller diameter (10mm) bars-for stools
  • Lapping
     Lapping is required when a bar isn’t long enough or a joint is required. Bars may be deliberately left short for constructability and transportation concerns. The preferred method of lapping where the two bars overlap each other for some minimum distance. This distance is called Lap length. These two bars are in physical contact and wired together. It does not represent an actual bend in the bar.
Picture20
Fig 2: Lapping and cranking detail
  • Other material used In Reinforcement Works
Binding Wires
R/f bars are jointed with using wires which is called “binding wires”. Hackers are used to bind these wires.
Cover Blocks
     They were made up of 1:3 ratio of cement mortar. Cover blocks should be immersed in water for 28 days to get the maximum strength.All the beams were checked to ensure adequate cover blocks are provided to the bottom and sides of the beam reinforcementMain bars of the columns were adjusted to ensure the covering requirements before concreting. Stools of correct height were used to maintain the require gap between top and bottom reinforcement nets and cover blocks were also provided to bottom reinforcement.
Picture21
Fig 3: Cover blocks
Cover to Reinforcement
  • Concrete cover for steel bar is much necessary to protect the steel against corrosion (rusting) and to provide resistance against fire.
  • For R.C.C. Slab and staircase the cover is 20 mm.
  • For RCC column the cover (To stirrups) 30mm.
  • In case of underground structures the cover is 50 mm.
  • In case of beams in superstructure (To stirrups) the cover is 25mm.
  • In case of ground resting floor slab (Top surface) and retaining walls the cover is 50m.

  • Stirrups
       Stirrups will be required at areas of high shear, such as bearing points and below large point loads.  Increasing concrete beam spans, to reduce the need for additional piers, has resulted in the need for the use of steel stirrups. Concrete beams vary in depth.  The deeper the beam, the more shear capacity.  When the depth is not adequate, steel stirrups must be added to increase the shear capacity of the beam.
       These stirrups are usually one piece of steel that is bent into a rectangular shape. The stirrup typically wraps around the bottom and top bars of the beams. A designer should specify the size, spacing and location along the length of the beam where the stirrups are required.  In my site specify the stirrup dimensions in our section drawings, so that the stirrup can be manufactured prior to installation. The installer should be careful to fabricate the stirrup from one piece of steel and adequately overlap each end.
Picture22
Fig 4: Bar Schedule for stirrups
  • Stools
Stools are used to separate the top reinforcement mesh and bottom reinforcement mesh. Dimension of the Stools could be change as requirement. Those should be strength enough to bear the loads without changing the gap of two layers. 12 mm or 16 mm bars are used to make the stools.
Picture24Picture23
Fig 5: Stools
Important  points to be checked.
  • Size of the bar
  • Length of the bar
  • Location of the bar
  • Position of the bar
  • Number of bars
  • Lap lengths
  • Correct cover of reinforcements and cover blocks
  • Spacing (in slab reinforcements and stirrups)
  • Direction of the bars (in slabs)
  • Dimensions of the element thickness of a slab, depth and width of a beam, etc…)
Columns, Beams, Slab Reinforcement
  • Column Reinforcement
      The column reinforcement bars should be stared from the Footing. The upper column reinforcement bars are cranked at the laps and connected. Special care should be taken in this to ensure the lap lengths. After erection of main reinforcements, cover blocks were attached to column reinforcements to maintain the required cover for column reinforcement. Most of Columns centers were located at intersections of grid lines.
Stirrup spacing
       According to the Column reinforcement details drawing the reinforcement detail for a typical internal Column, from to basement to ground floor is as follows.
       Column stirrups were tightened up to beam bottom level and rest is tightened once beam reinforcement is fabricated. So Bar benders was instructed how to provide the stirrups. Mark the stirrup spacing from the basement floor level in the Column main bars with a chalk as follow the detail drawing.
E.g.:
Picture25Picture26
Fig 6:  Section of column Reinforcement
Bar Schedule for Footing, Column up to DPC and Column.
E.g-
Picture2
Footing
Size – 1000 x 1000 x 250
R/f Details – Y10 at 225 C/C (B) Both ways
Picture3
Table 1: Schedule for Footing, Column up to DPC and Column
  • Beam Reinforcement
   Beam is a horizontal structural member resting on two or more supports. It is used to transfer the load to the columns.Beam reinforcements are arranged after the construction of beam and slab formwork.
The method adopted for the arrangement of beam reinforcements is as follows:
    First the top most reinforcement bars are hung over the beam formwork and then the stirrups are placed and bound at correct positions. Thereafter the bottom reinforcement bars are placed and bound to the stirrups. After that the rest of the reinforcement bars and tension bars are inserted into the cage according to structural drawings. Then cover blocks are fixed to bottom and side reinforcements before placing the concrete.
Consideration for give lap length
Picture27
Fig 7: Reinforcement for beams
    Top reinforcement of the beam shall be lapped at the middle of the span of between two supports. Bottom reinforcement of the beam shall be lapped at the end of the span of the two supports. Considering the region where the maximum bending movement is existing.
       Lapping is did the place which the tension is didn’t act. Normally 2/3 of the length is choosing for lapping. When lapping top & bottom re-bar, it is better to follow the following method.Otherwise, it might cause to reduce the concrete covering thickness of the topmost& bottom most slab reinforcement.
Picture28
Fig 8: Reinforcement  for beams
Anchorage (bond) in concrete
Because the actual bond stress varies along the length of a bar anchored in a zone of tension. The main requirement for safety against bond failure is to provide a sufficient extension of the length of the bar beyond the point where the steel is required to develop its yield stress and this length must be at least equal to its development length. However, if the actual available length is inadequate for full development, special anchorages must be provided, such as bends, hooks.
E.g- (Anchorage length 45 d (for top bars),12 d (for bottom bars)) where “d”, “Ø”  is diameter of the Bar.
Anchorage length Calculation
E.g.:-  20 mm diameter bar
Picture29
Fig 9: Anchorage length
Bending length = 112.5- (Cover (25 mm)+ Stirrup (10 Ø))
= 72.5mm
Anchorage length (x) = 45 x diameter of the bar(20 Ø)
= 827.5 mm
Bar schedule for Beam
Picture6
Picture7
Table 2: Bar Schedule for Beam
  • Slab Reinforcement
Slab reinforcement is the most important part of the structure. It is important to have an idea on slab reinforcement detailing. Following basic thing could be studied in drawing on slab reinforcement detailing.

Distribution bar reinforcement

Small diameter bars, usually at right angles to the main reinforcement, intended to spread a concentrated load on a slab and to prevent cracking.Standard method used for indicated the slab top & bottom reinforcement.
Picture30
First step of the fixing of slab reinforcement was placed the bottom most R/F (B1) of the slab. Before placing the re-bar, correct spacing given in the detailing drawing were marked by using piece of choke on the slab formwork. After placed the (B1) R/F then placed the (B2) R/F and bound both R/F layers together by using binding wire. Then cover blocks for bottom most R/F were fixed. Finally, Top R/F (T2), Topmost R/F (T1)& distribution bars were placed according to the drawing and fixed together by using binding wire. Then Stools were fixed to separate the both top & bottom R/F net as fulfilled the thickness.
DCIM101MEDIA
Fig 10:  Reinforcement of a slab
Bar crank
Bar cranking is the process of bending up the bottom steel bars in upward direction. It is mainly to prevent upward bending moment near the joint. Also useful for attaching stirrup bar effectively. Cranking is also used in two way slabs.
  • Bar schedule for Slab
Picture8
Picture9
Table 3 : Bar schedule for Slab
  • Bar schedule for some other structures
 Bar schedule for Plinth 
Picture4
Picture33
Table 4: Bar schedule for Plinth
Bar schedule for Stiffener column, Sill beam and Lintel beam
Picture10
Picture11
Picture31
Table 5: Bar schedule for Stiffener column, Sill beam and Lintel beam

Formation Of Bar Bending Schedule

A list of reinforcement bars is called bar bending schedule (or schedule of bars), a given RCC work thing, and is displayed in a form of tabular layout for simple graphical reference. The following table epitomizes all the required details of bars such as diameter, shape of bending, length of each bent and straight portions, angles of bending, total length of each bar, and number of each sort of bar. During the preparation of an estimate of quantities this information will help unconditionally.
The figure below portrays the shape and proportions of hooks and bends in the reinforcement bars – these are customary proportions that are attached to:
(a) Length of one hook = (4d ) + [(4d+ d )] – where, (4d+ d ) relates to the curved portion = 9d.
(b) The supplementary length (la) that is introduced in the plain, straight end-to-end length of a reinforcement bar owing to being bent up at θ° say 30° to 60°, but it is usually 45°) = l1 – l2 = la
Where,
formulaformula

We get different values in respect to the θ° = 30° 45° 60° as follows :
formula
The following figure demonstrates the method to determine the length of hooks and the total length of a given steel reinforcement.
Formation Of Bar Bending Schedule

1 comment:

  1. Nice Article thanks for sharing you can find more about Bar Bending Schedule Basics here Read More

    ReplyDelete