Wednesday 13 July 2022

Thumb Rules for Civil Engineering In Construction

 

Thumb Rules for Civil Engineering In Construction


1. Thumb Rule for Concrete Volume

The volume of concrete required = 0.038 m3/square feet area

Example:-If Plan Area = 40 x 20 = 800 Sq. m.

So, for the plan area of 800 Sq. m. the area the total volume of concrete required

= 800 x 0.038m3 = 30.4m3


2. Thumb Rule for Steel Quantity for Slab, Beams, Footings & Columns

Following are some important thumb rules for steel calculation for slabbeamcolumn, and footings.

Steel required in residential buildings = 4.5 Kgs – 4.75 Kgs / sq. Ft.

Steel required For Commercial buildings = 5.0 Kgs-5.50 Kgs/Sq. Ft.

You can also use BN Datta recommendations for the more accurate result,

The following recommendations Thumb Rules For Civil Engineering are given in B N Datta for the Steel quantity used in different members of the building.

3. Percentage of Steel in Structural Members

Following are thumb rules for reinforcement in concrete members,

1) Slab – 1% of the total volume of concrete (Slab steel calculation thumb rule)
2) Beam – 2% of the total volume of concrete
3) Column – 2.5% of total volume of concrete
4) Footings – 0.8% of the total volume of concrete

Example:

How to calculate the steel quantity of slab having the Length, width, and depth of the slab is 5m x 4m x 0.15m

Step 1: Calculate the Volume of Concrete:

The Total Volume of Concrete for given Slab = 5 x 4 x 0.15

= 3m3

Step 2: Calculate The Steel Quantity Using Formula:

As per the guidelines are given in the BN Dutta reference book the steel quantity of slab is 1% of the total volume of concrete utilized.

Thumb rule to estimate Steel quantity of above slab = Volume of Concrete x Density of Steel x % of Steel of Member

Steel weight required for above slab = 3 x 7850 x 0.01 = 235Kgs

For accurate estimation, you can refer to Bar Bending Schedule

Read More: Civil Calculator (Civil Engineering Calculator)


4. Thumb Rules For Shuttering Work

Shuttering costs are taken as 15-18% of the total construction of the buildingShuttering work is done to bring the concrete in Shape. The Thumb rule to estimate the shuttering required is 6 times the quantity of concrete or 2.4 times of the Plinth area.

For example, the concretquantity is 0.5m3, then

Area of Shuttering is 0.5 x 6 = 3m2

Components of Shuttering

Shuttering Ply Quantity estimation

The Shuttering plate Ply, Battens, Nails are components of Shuttering.

Suppose, The Shuttering Ply has a lengthwidth depth of 2.44 x 1.22 x 0.012

The No. of Shuttering Ply Sheets = 0.22 times of Shuttering

Suppose, the Shuttering Area = 3m

Then Ply required for shuttering = 0.22 x 3 = 0.66m2


5. Battens Quantity Calculation

Shuttering Batten usually has a length & width of 75mm x 40mm.

Batten Quantity = 19.82 x No. of Ply Sheets

If work requires 25 Ply sheets, the total quantity of Battens are 19.82 x 25 = 495 Battens

Nails & Binding Wire Quantity in Shuttering:

Approximately75 grams of Nails were used in the shuttering of the 1m2 area.

75gms of Binding wire is used for every 1m2 of Shuttering.

Thumb rule for Shuttering oil estimation :

Shuttering oil is applied on the shuttering plate surface used to de-frame or de-assemble from the concrete easily.

Total required Shuttering oil  = 0.065 x Total Area of Shuttering

(or)

For every 15m2 of shuttering 1 liter of shuttering oil is consumed.

Example :

If, total area of shuttering is 15 m2, then Shuttering oil Consumption = 0.065 x 15 = 0.975.

Read More: 17 Tips For How To Reduce Construction Cost


6. Thumb Rule for Cement, Sand, Coarse Aggregate Quantity Calculations

Note: 1 bag of cement = 50Kgs

Thumb rule for Cement required in BrickworkCement Masonry Plastering work in construction.


7. Thumb Rules For Civil Engineers for Brickwork

following are Thumb Rules for civil engineering for brickwork and cement quantity calculations.

Brickwork for 1m3Cement Qty in m3Cement Qty in Bags
230 mm Brickwork
0.876m325.4 Bags
115 mm Brickwork0.218m36.32 Bags

8. Thumb Rules For Cement Masonry Quantity

Cement Masonry Type & MixCement Qty in BagsCement Qty in Kgs
200mm in Cement Masonry work
of Ratio 1:6
0.124Bags/m2
6.2Kgs/m2
150mm in Cement Masonry work
of Ratio 1:6
0.093Bags/m2
4.65Kgs/m2
200mm in Cement Masonry work
of Ratio 1:4
0.206Bags/m2
10.3Kgs/m2
150mm in Cement Masonry work
of Ratio 1:4
0.144Bags/m2
7.2Kgs/m2
100mm in Cement Masonry work
of Ratio 1:4
0.103Bags/m2
5.15Kgs/m2

Thanks to 
Civil Engineering Calculator
Er. SP.ASWINPALANIAPPAN., M.E.,(Strut/.,)
Structural Engineer
http://civilbaselife.blogspot.com/

No comments:

Post a Comment